Estimate (VDI) move to API
All Project Committees will follow the Project Standard Committee Guidelines and Mission.
Status: Not Started / CIECA Staff Review / Committee(s) Review / Rejected / *In Progress / Completed
Dates
Project Proposed | Project Reviewed by CIECA Staff | Submitted to Committee(s) Review | Project Started | Rejected/Completed |
---|---|---|---|---|
Nov 21, 2023 | Nov 22, 2023 | Dec 4, 2023 | Feb 1, 2024 |
Background
Author of Project Request: Phil Martinez and CIECA Staff.
Objective: Identify the Data needed to create Estimate API messages for industry segments to electronically communicate.
Expected Outcome(s): Data Elements identified and added to the CAPIS Data Dictionary, Code List identified and added to the CAPIS Code List, and Test Instances.
Impacted/Interested Industry Segments:
Problem Statement:
Scope:
Must have: Identify Data Elements for Estimate | Add API Data Elements to CAPIS schema after approval from Architecture. |
Must have: Add Code List | Add Code List after approval from Architecture. |
Must have: Create Test Instances | Add Test Instances |
Nice to have: | |
Not in scope: | |
Risk to scope: |
CIECA Products Impacted:
Benefits to Industry:
Releases and Task:
Scheduled Release:
Task report
Edit to setupJira Report: